City of Ekurhuleni Metropolitan Municipality v Takubiza Trading & Projects CC and Others [2022] ZASCA 82; 2023 (1) SA 44 (SCA), delivered on 3 June 2022.
The dispute
Every tender invitation states a period during which bids remain valid and open for acceptance. In this matter the City of Ekurhuleni sought to extend that period on its very last day, and then awarded the tender after the original validity period had run out. Takubiza, represented by Albert Hibbert Attorneys, challenged the award.
What the Supreme Court of Appeal decided
The Court rejected the Municipality’s argument that its late request for an extension saved the process. Once the validity period expired, the tender process was complete, albeit unsuccessfully. There were no longer any valid bids capable of acceptance, and the Municipality had no power to extend a period that had already lapsed. The Municipality’s appeal was dismissed.
The Court also expressed its displeasure at the size of the appeal record, much of which was irrelevant, and ordered that the Municipality’s attorneys could not recover the costs of preparing, perusing or copying it.
Why it matters
For organs of state, the judgment is a reminder that the procurement timetable is not a formality: if an award cannot be made within the validity period, any extension must be properly obtained before the period expires. For bidders, it confirms that an award made outside the validity period can be challenged and set aside.
If you have been affected by a tender award made after the validity period expired, or any other irregular award, speak to our tender dispute attorneys.